Solar site survey checklist: what to confirm with the homeowner before dispatch
Solar PV installations stall on the same avoidable issues: an old asbestos roof nobody mentioned, no space for scaffolding along the gable, a meter cabinet with zero spare slots, or an unheated shed planned for a battery. Asking the homeowner for structured answers and two mandatory photos before you book a surveyor or scaffolding crew shows those blockers early.
Updated November 20, 2026What this pre-visit solar checklist covers — and what it does not
This checklist does not replace roof layout design, shading analysis, structural checks or grid-operator notifications. It answers one operational question before anyone drives out: are the roof, scaffold corridor, meter cabinet and inverter location ready for the job as quoted?
Send the link right after the customer confirms interest and before you lock in scaffolding or an installation crew. You can also combine it with our general pre-installation site readiness checklist.
The solar PV and battery site survey checklist
Every row below matches InstallCue’s built-in Solar PV with battery storage starter template. Column three marks the exact answer that turns into an automatic blocker until your team resolves it.
| Question to the customer | Ask for | Stops the job when |
|---|---|---|
| Photos of every roof surface to be used | Mandatory photo per roof side from the ground or garden showing the full surface | Missing photo |
| Roof covering | Concrete tiles, clay tiles, slate, metal/trapezoidal sheet, flat roof (bitumen/membrane), other | Not a blocker on its own; determines mounting hardware |
| Is the roof free of known damage, leaks and asbestos (e.g. old corrugated fibre-cement sheets)? | Yes or no | No — roof damage or possible asbestos must be clarified first |
| Is there room for a scaffold along the house (about 1 m next to the wall, no obstacles)? | Yes or no | No — scaffold clearance is not yet available |
| Photo of the open meter cabinet | Mandatory photo with the door open showing meters, fuses and spare slots clearly | Missing photo |
| Is there free space in the meter cabinet for an additional meter or control device? | Yes, no, or “Don’t know” (the photo lets your team judge) | No — a cabinet upgrade must be planned first |
| Planned location for inverter and battery | Optional photo showing the wall and floor (dry, frost-free room) | Context for your electrical team |
| Distance from the meter cabinet to the planned inverter location | Measured estimate in metres, plus customer confirmation that values were checked on site | Helps quote cable length and wall penetrations |
| Is there Wi-Fi or a network socket at the inverter location? | Yes or no | Not a blocker on its own; flags whether a repeater or cable is needed |
The two mandatory photos that prevent wasted site visits
- Every planned roof surface from the ground: reveals dormers, skylights, chimneys, roof pitch and obvious damage before scaffolding is ordered.
- The open meter cabinet straight-on: lets your electrician spot outdated distribution boards, missing spare ways or cramped spaces in seconds — even when the homeowner answers “Don’t know”.
Never rely on a customer’s verbal reassurance about the meter cabinet. One straight-on photo of the open cabinet settles more technical questions than ten emails.
How to turn the checklist into a tracked Go/No-Go decision
- Send one mobile-friendly link with no app download or customer account.
- Set a decision deadline ahead of scaffolding booking so up to two automatic email reminders chase missing answers.
- Let deterministic blocker rules flag asbestos risk, missing scaffold space or a full meter cabinet immediately when saved.
- Have a reviewer on your team approve the site as Ready and hand the install pack link or ZIP export to the crew.
See how catching blockers before dispatch works in practice, or try the heat pump survey form if your team installs both trades.
Frequently asked questions
- Does a homeowner self-survey replace an on-site solar technical inspection?
- No. It acts as a structured pre-check before you commit scaffolding or a crew, flagging roof condition, access and meter-cabinet issues early. Roof layout, structural assessment and electrical design stay with your engineers.
- What if the homeowner does not know whether the meter cabinet has spare space?
- Let them select “Don’t know” and upload a clear photo of the open cabinet. Your electrician can then review the photo and decide whether an upgrade is needed without stalling the customer.
- How does InstallCue support solar PV site surveys?
- InstallCue includes the Solar PV with battery storage starter template out of the box. Customers complete one link on their phone without an account, blockers trigger automatically, and your team approves the site before handing the install pack to the crew.